slava.energy: UK renewable energy projects
Penrhys Wind Farm/Ferndale Power Factory
REPD record 3660. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 6.4 MW
- Status
- Operational
- Operator
- John Laing Environmental Assets Group
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Rhondda Cynon Taf
- Planning reference
- 03/0226
- Turbines
- 8
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2013-11-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-02-11: Planning Application Submitted
- 2004-01-09: Planning Permission Refused
- 2005-03-01: Appeal Granted
- 2005-03-01: Planning Permission Granted
- 2010-04-01: Under Construction
- 2011-06-08: Operational
- 2016-03-01: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3660. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.