slava.energy: UK renewable energy projects
The Michelin Tyre Factory - Ballymena
REPD record 3680. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 4.6 MW
- Status
- Operational
- Operator
- Ecotricity
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Mid and East Antrim
- Planning reference
- G/2009/0470/FUL
- Turbines
- 2
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2013-04-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-07-24: Planning Application Submitted
- 2010-02-07: Planning Permission Granted
- 2012-09-11: Under Construction
- 2013-02-25: Operational
- 2014-02-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3680. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.