REPD record 3703. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 4 MW
- Status
- Operational
- Operator
- Renewable Energy Generation
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- Wyre
- Planning reference
- 09/00352/FULMAJ
- Turbines
- 2
- Turbine size
- 2 MW
- Record last updated in REPD
- 2015-03-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-05-12: Planning Application Submitted
- 2009-12-02: Planning Permission Refused
- 2010-12-16: Appeal Granted
- 2010-12-16: Planning Permission Granted
- 2012-08-01: Under Construction
- 2013-06-17: Operational