Wingates Wind Farm
REPD record 3754. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 15 MW
- Status
- Operational
- Operator
- Ventient (formerly Infinis)
- County
- Northumberland
- Region
- North East
- Country
- England
- Planning authority
- Northumberland
- Planning reference
- C/09/00084/CCMEIA
- Turbines
- 6
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2013-06-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2008-12-05: Planning Application Submitted
- 2011-05-04: Planning Permission Granted
- 2012-08-01: Under Construction
- 2013-03-31: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3754. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.