Wathegar wind farm
REPD record 3757. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Private Developer
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- 10/00042/FULCA
- Turbines
- 5
- Turbine size
- 2 MW
- Record last updated in REPD
- 2013-06-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-02-09: Planning Application Submitted
- 2010-05-21: Planning Permission Granted
- 2012-06-01: Under Construction
- 2013-03-31: Operational
- 2019-05-21: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3757. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.