Treading Wind Farm - Fenland
REPD record 3785. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 15 MW
- Status
- Appeal Refused
- Operator
- Wind Ventures
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/YR11/0113/F
- Turbines
- 6
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2013-10-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-01-21: Planning Application Submitted
- 2012-07-03: Planning Permission Refused
- 2013-10-09: Appeal Refused