Lillyhall Wind Farm
REPD record 3794. Status: Secretary of State - Refusal.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 9.2 MW
- Status
- Secretary of State - Refusal
- Operator
- FCC Environment
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- 02/2012/9011
- Turbines
- 4
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2015-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-10-30: Planning Application Submitted
- 2014-02-28: Planning Permission Refused
- 2015-04-14: Appeal Lodged
- 2015-11-03: Secretary of State - Refusal
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3794. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.