slava.energy: UK renewable energy projects
Tansterne Straw-Burning Power Station
REPD record 38. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 10 MW
- Status
- Revised
- Operator
- G B Bio
- County
- Humberside
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- East Riding of Yorkshire
- Planning reference
- 06/09030/STOUT
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2009-03-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2006-11-13: Planning Application Submitted
- 2007-08-06: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 38. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.