Myreton Crossroads
REPD record 3804. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 1.6 MW
- Status
- Operational
- Operator
- Seren Energy
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Moray
- Planning reference
- 09/00247/FUL
- Turbines
- 2
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2013-09-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-02-09: Planning Application Submitted
- 2009-12-10: Planning Permission Refused
- 2010-07-19: Appeal Granted
- 2010-07-19: Planning Permission Granted
- 2012-03-01: Under Construction
- 2013-07-05: Operational
- 2019-07-19: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3804. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.