slava.energy: UK renewable energy projects
Lingo Wind Farm
REPD record 3844. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12.5 MW
- Status
- Appeal Refused
- Operator
- Lingo Wind Energy Ltd
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 12/00129/EIA
- Turbines
- 5
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2013-10-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-01-23: Planning Application Submitted
- 2013-01-31: Planning Permission Refused
- 2013-10-04: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3844. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.