slava.energy: UK renewable energy projects
Glendoe Hydro Scheme
REPD record 388. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Large Hydro
- Capacity
- 100 MW
- Status
- Operational
- Operator
- Scottish and Southern Energy (SSE)
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- IN2003459
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2009-07-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-07-28: Planning Permission Expired
- 2003-05-01: Planning Application Submitted
- 2005-07-28: Planning Permission Granted
- 2006-05-01: Under Construction
- 2008-12-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 388. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.