Glendoe Hydro Scheme

REPD record 388. Status: Operational.

Facts

As published by REPD, release Q3 2026.

Technology
Large Hydro
Capacity
100 MW
Status
Operational
Operator
Scottish and Southern Energy (SSE)
County
Highland
Region
Scotland
Country
Scotland
Planning authority
Scottish Government (S36)
Planning reference
IN2003459
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2009-07-17

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 388. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.