slava.energy: UK renewable energy projects
Ballyreagh, Tempo
REPD record 3954. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2.5 MW
- Status
- Abandoned
- Operator
- TCI Renewables
- County
- Co. Fermanagh
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Fermanagh and Omagh
- Planning reference
- L/2006/2371/F
- Turbines
- 1
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2016-02-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2006-12-15: Planning Application Submitted
- 2009-05-11: Planning Permission Granted
- 2015-05-11: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3954. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.