slava.energy: UK renewable energy projects
Aston Grange Farm
REPD record 3967. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12 MW
- Status
- Appeal Refused
- Operator
- Tegni Cymru
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire West and Chester
- Planning reference
- 05-1059-fum
- Turbines
- 4
- Turbine size
- 3 MW
- Record last updated in REPD
- 2011-11-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2005-06-20: Planning Application Submitted
- 2006-10-11: Planning Permission Refused
- 2008-11-05: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 3967. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.