Ardoch Farm (East Renfrewshire)
REPD record 4017. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3.9 MW
- Status
- Abandoned
- Operator
- Private Developer
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- East Renfrewshire
- Planning reference
- 2003/0022/TP
- Turbines
- 3
- Turbine size
- 1.3 MW
- Record last updated in REPD
- 2011-12-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-01-15: Planning Application Submitted
- 2004-09-02: Planning Permission Granted
- 2015-09-02: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4017. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.