slava.energy: UK renewable energy projects
Church Hill
REPD record 4047. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 18.4 MW
- Status
- Operational
- Operator
- Greencoat (formerly Energia Renewables)
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Derry City and Strabane
- Planning reference
- J/2005/0358/F
- Turbines
- 8
- Turbine size
- 2 MW
- Record last updated in REPD
- 2019-01-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2005-04-06: Planning Application Submitted
- 2007-04-26: Planning Permission Granted
- 2011-04-26: Planning Permission Expired
- 2011-05-01: Under Construction
- 2012-06-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4047. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.