Slieve Divena Phase 2 Wind Farm
REPD record 4054. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 18.8 MW
- Status
- Operational
- Operator
- Scottish and Southern Energy (SSE)
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Fermanagh and Omagh
- Planning reference
- K/2005/1691/F
- Turbines
- 8
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2017-11-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2005-09-13: Planning Application Submitted
- 2007-06-06: Planning Permission Granted
- 2016-05-30: Under Construction
- 2017-02-16: Operational
- 2018-02-20: Planning Permission Expired