slava.energy: UK renewable energy projects
Common Barn Wind Farm
REPD record 4076. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 6.2 MW
- Status
- Operational
- Operator
- TCI Renewables
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Huntingdonshire
- Planning reference
- 1200803FUL
- Turbines
- 3
- Turbine size
- 3 MW
- Record last updated in REPD
- 2019-12-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-05-15: Planning Application Submitted
- 2012-12-05: Planning Permission Refused
- 2013-07-11: Appeal Granted
- 2013-07-11: Planning Permission Granted
- 2015-07-11: Planning Permission Expired
- 2018-01-15: Under Construction
- 2019-05-09: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4076. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.