Meikle Carewe
REPD record 4109. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 10 MW
- Status
- Operational
- Operator
- The Renewables Infrastructure Group (TRIG)
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2006/3934
- Turbines
- 12
- Turbine size
- 0.85 MW
- Record last updated in REPD
- 2014-06-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2000-05-20: Planning Permission Expired
- 2006-11-29: Planning Application Submitted
- 2010-05-20: Planning Permission Granted
- 2012-07-26: Under Construction
- 2013-07-30: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4109. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.