Easter Tolmauds
REPD record 4133. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 1.6 MW
- Status
- Operational
- Operator
- Frank A Smart & Son Ltd
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2014/1890
- Turbines
- 2
- Turbine size
- 0.8 MW
- Record last updated in REPD
- 2020-09-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-05-20: Planning Application Submitted
- 2014-08-22: Planning Permission Refused
- 2014-10-15: Appeal Lodged
- 2015-05-29: Appeal Granted
- 2015-05-29: Planning Permission Granted
- 2016-02-01: Under Construction
- 2016-10-15: Operational
- 2018-05-29: Planning Permission Expired
Position not held by REPD.