slava.energy: UK renewable energy projects
Winwick
REPD record 4164. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12.3 MW
- Status
- Operational
- Operator
- Blue Energy
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- DA/2010/0400
- Turbines
- 6
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2016-08-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-05-17: Planning Application Submitted
- 2012-07-13: Appeal Granted
- 2012-07-13: Planning Permission Granted
- 2012-07-13: Planning Permission Refused
- 2015-04-15: Under Construction
- 2016-06-30: Operational
- 2017-07-13: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4164. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.