slava.energy: UK renewable energy projects
Abergorki Wind Farm
REPD record 4198. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 13.5 MW
- Status
- Planning Permission Granted
- Operator
- Thrive Renewables
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Rhondda Cynon Taf
- Planning reference
- 13/0663/10
- Turbines
- 3
- Turbine size
- 4.5 MW
- Record last updated in REPD
- 2024-11-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-06-27: Planning Application Submitted
- 2015-07-23: Planning Permission Granted
- 2018-07-23: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4198. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.