Ingst Hill Wind Farm/ M48 Wind Farm
REPD record 4222. Status: Appeal Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 5.2 MW
- Status
- Appeal Withdrawn
- Operator
- REG Windpower
- County
- Avon
- Region
- South West
- Country
- England
- Planning authority
- South Gloucestershire
- Planning reference
- PT12/4071/F
- Turbines
- 2
- Turbine size
- 2.6 MW
- Record last updated in REPD
- 2015-10-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-12-05: Planning Application Submitted
- 2014-12-17: Planning Permission Refused
- 2015-07-27: Appeal Lodged
- 2015-10-29: Appeal Withdrawn
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4222. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.