slava.energy: UK renewable energy projects
Wryde Croft
REPD record 4248. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 26 MW
- Status
- Operational
- Operator
- Renewable Energy Systems (RES)
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Peterborough
- Planning reference
- 07/01411/FUL
- Turbines
- 13
- Turbine size
- 2 MW
- Record last updated in REPD
- 2016-02-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2006-07-01: Planning Application Submitted
- 2008-10-22: Planning Permission Refused
- 2010-04-01: Appeal Granted
- 2010-04-01: Planning Permission Granted
- 2014-09-01: Under Construction
- 2016-02-20: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4248. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.