Blairadam Wind Farm

REPD record 4270. Status: Planning Permission Refused.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
22.6 MW
Status
Planning Permission Refused
Operator
Partnerships for Renewables Development Company Limited
County
Fife
Region
Scotland
Country
Scotland
Planning authority
Fife
Planning reference
14/00008/EIA
Turbines
11
Turbine size
2.05 MW
Record last updated in REPD
2016-11-01

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4270. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.