slava.energy: UK renewable energy projects
Crookedstane Farm
REPD record 4355. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 11.4 MW
- Status
- Planning Permission Expired
- Operator
- BayWa r.e. (formerly Forsa)
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- South Lanarkshire
- Planning reference
- CL/13/0206
- Turbines
- 4
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2019-12-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-06-13: Planning Application Submitted
- 2016-01-19: Planning Permission Granted
- 2019-01-19: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4355. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.