Earlseat
REPD record 4363. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 18.4 MW
- Status
- Operational
- Operator
- The Renewables Infrastructure Group (TRIG)
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 10/03539/EIA
- Turbines
- 8
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2014-08-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-09-17: Planning Application Submitted
- 2011-03-02: Planning Permission Expired
- 2012-03-02: Planning Permission Granted
- 2013-10-30: Under Construction
- 2014-07-30: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4363. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.