slava.energy: UK renewable energy projects
Fenrother Wind Farm
REPD record 4366. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 15 MW
- Status
- Appeal Refused
- Operator
- Energiekontor UK
- County
- Northumberland
- Region
- North East
- Country
- England
- Planning authority
- Northumberland
- Planning reference
- 12/02500/RENEIA
- Turbines
- 5
- Turbine size
- 3 MW
- Record last updated in REPD
- 2014-08-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-09: Planning Application Submitted
- 2013-01-16: Planning Permission Refused
- 2014-08-07: Appeal Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4366. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.