Kilton Wind Turbine

REPD record 4387. Status: Planning Permission Refused.

Facts

As published by REPD, release Q3 2026.

Technology
Wind Onshore
Capacity
2.5 MW
Status
Planning Permission Refused
Operator
TNEI Services
County
Cleveland
Region
North East
Country
England
Planning authority
Redcar and Cleveland
Planning reference
R/2014/0433/FF
Turbines
1
Turbine size
2.5 MW
Record last updated in REPD
2014-12-05

Status history

Dated status events as published by REPD, release Q3 2026.

Position not held by REPD.