Leacann Hydro
REPD record 442. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Small Hydro
- Capacity
- 1 MW
- Status
- Operational
- Operator
- DHG Hydro
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Argyll and Bute
- Planning reference
- 13/01481/PP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-01-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-29: Planning Application Submitted
- 2013-12-06: Planning Permission Granted
- 2015-03-20: Under Construction
- 2016-08-15: Operational
- 2019-12-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 442. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.