Blackwood Wind Farm
REPD record 4453. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 10.3 MW
- Status
- Appeal Refused
- Operator
- Force 9 Energy
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Dumfries and Galloway
- Planning reference
- 12/P/3/0060
- Turbines
- 5
- Turbine size
- 2.05 MW
- Record last updated in REPD
- 2016-10-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-02-14: Planning Application Submitted
- 2016-05-26: Planning Permission Refused
- 2016-08-26: Appeal Lodged
- 2016-08-26: Appeal Refused
Position not held by REPD.