Airies Farm
REPD record 4462. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 35 MW
- Status
- Operational
- Operator
- NTR
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Dumfries and Galloway
- Planning reference
- 12/P/1/0271
- Turbines
- 14
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2020-08-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-24: Planning Application Submitted
- 2013-03-01: Planning Permission Granted
- 2014-03-01: Planning Permission Expired
- 2016-02-08: Under Construction
- 2017-03-15: Operational