Halifax Farm
REPD record 4493. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 1.6 MW
- Status
- Operational
- Operator
- Wentworth and Harper
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Hinckley and Bosworth
- Planning reference
- 14/00532/FUL
- Turbines
- 1
- Turbine size
- 1.6 MW
- Record last updated in REPD
- 2016-10-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-02: Planning Application Submitted
- 2014-09-18: Planning Permission Granted
- 2015-05-15: Under Construction
- 2015-09-01: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4493. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.