Hawton Wind Farm
REPD record 4532. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 9 MW
- Status
- Operational
- Operator
- Temporis Capital
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Newark and Sherwood
- Planning reference
- 11/01588/FULM
- Turbines
- 3
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2017-10-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-12-05: Planning Application Submitted
- 2012-08-22: Planning Permission Refused
- 2012-10-10: Appeal Lodged
- 2014-09-29: Appeal Granted
- 2014-09-29: Planning Permission Granted
- 2016-09-16: Under Construction
- 2017-03-16: Operational
- 2017-09-29: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4532. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.