Roseland Community Wind Farm
REPD record 4533. Status: Secretary of State - Refusal.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 12 MW
- Status
- Secretary of State - Refusal
- Operator
- Roseland Community Energy Trust
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Bolsover
- Planning reference
- 12/00159/FULEA
- Turbines
- 6
- Turbine size
- 2 MW
- Record last updated in REPD
- 2015-03-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-04-25: Planning Application Submitted
- 2013-07-19: Planning Permission Refused
- 2014-01-30: Appeal Lodged
- 2014-06-01: Secretary of State - Intervened
- 2015-03-16: Secretary of State - Refusal
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4533. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.