Altamuskin Extension
REPD record 4557. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 7.1 MW
- Status
- Operational
- Operator
- Altamuskin Windfarm (Energia)
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Fermanagh and Omagh
- Planning reference
- K/2011/0239/F
- Turbines
- 3
- Turbine size
- 2.35 MW
- Record last updated in REPD
- 2017-05-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-04-13: Planning Application Submitted
- 2015-01-28: Planning Permission Granted
- 2016-03-01: Under Construction
- 2017-03-15: Operational
- 2020-01-28: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4557. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.