slava.energy: UK renewable energy projects
Sheildaig Hydro Project
REPD record 459. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Small Hydro
- Capacity
- 2.1 MW
- Status
- Planning Permission Refused
- Operator
- Highland Light and Power
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Highland
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2005-03-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-05-05: Planning Application Submitted
- 2004-03-16: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 459. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.