Tullymurdoch Wind Farm
REPD record 4599. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 14.4 MW
- Status
- Operational
- Operator
- Temporis Capital
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 12/01423/FLL
- Turbines
- 7
- Turbine size
- 2.05 MW
- Record last updated in REPD
- 2018-04-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-13: Planning Application Submitted
- 2013-03-13: Planning Permission Refused
- 2013-08-13: Appeal Lodged
- 2014-09-03: Appeal Granted
- 2014-09-03: Planning Permission Granted
- 2017-08-24: Under Construction
- 2017-09-03: Planning Permission Expired
- 2018-01-23: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4599. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.