slava.energy: UK renewable energy projects
Fen Lane wind farm
REPD record 4617. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 17.5 MW
- Status
- Appeal Refused
- Operator
- Energiekontor UK
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- East Lindsey
- Planning reference
- N/056/01036/14
- Turbines
- 7
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2017-10-31
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-06-27: Planning Application Submitted
- 2015-03-04: Appeal Lodged
- 2017-10-25: Appeal Refused
- 2017-10-25: Planning Permission Refused
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4617. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.