Mid Hill - Phase II
REPD record 4627. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 18.4 MW
- Status
- Operational
- Operator
- Fred Olsen Renewables
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- SO30179PF
- Turbines
- 8
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2016-02-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-02-12: Planning Application Submitted
- 2005-06-03: Planning Permission Granted
- 2011-06-03: Planning Permission Expired
- 2014-08-25: Under Construction
- 2014-12-02: Operational
Position not held by REPD.
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4627. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.