Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 13.8 MW
- Status
- Revised
- Operator
- University of St Andrews
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 11/02799/EIA
- Turbines
- 6
- Turbine size
- 2.3 MW
- Record last updated in REPD
- 2017-01-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-06-20: Planning Application Submitted
- 2012-10-01: Planning Permission Refused
- 2013-10-07: Appeal Granted
- 2013-10-07: Planning Permission Granted
- 2016-10-07: Planning Permission Expired