Pigeon Top
REPD record 4650. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 27 MW
- Status
- Under Construction
- Operator
- Energia
- County
- Co. Tyrone
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Fermanagh and Omagh
- Planning reference
- K/2011/0592/F
- Turbines
- 9
- Turbine size
- 3 MW
- Record last updated in REPD
- 2020-03-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-09-26: Planning Application Submitted
- 2012-11-15: Planning Permission Granted
- 2015-12-17: Under Construction
- 2017-11-15: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4650. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.