Chiplow
REPD record 4657. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 8.2 MW
- Status
- Operational
- Operator
- Blue Energy
- County
- Norfolk
- Region
- Eastern
- Country
- England
- Planning authority
- King's Lynn and West Norfolk
- Planning reference
- 10/00883/FM
- Turbines
- 5
- Turbine size
- 2 MW
- Record last updated in REPD
- 2016-08-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-05-26: Planning Application Submitted
- 2011-05-10: Planning Permission Refused
- 2012-05-24: Appeal Granted
- 2012-05-24: Planning Permission Granted
- 2015-03-31: Under Construction
- 2016-04-30: Operational
- 2016-05-24: Planning Permission Expired