slava.energy: UK renewable energy projects
Skinners Farm
REPD record 4700. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6 MW
- Status
- Appeal Refused
- Operator
- Green Energy UK Direct
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Sevenoaks
- Planning reference
- 14/03361/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-09-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-10-28: Planning Application Submitted
- 2015-01-08: Planning Permission Refused
- 2015-06-01: Appeal Lodged
- 2015-12-15: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4700. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.