Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Public Power Solutions& Swindon Borough Council
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/LDO/15/1182
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-08-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-06: Planning Application Submitted
- 2015-08-10: Planning Permission Granted
- 2017-01-18: Under Construction
- 2017-03-31: Operational
Open this area on the map