Stormy Down (Waste AD)
REPD record 4786. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Severn Trent (formerly Agrivert)
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Bridgend
- Planning reference
- P/14/700/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-10-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-10-23: Planning Application Submitted
- 2015-04-19: Planning Permission Granted
- 2015-08-25: Under Construction
- 2016-10-03: Operational
- 2018-04-19: Planning Permission Expired