slava.energy: UK renewable energy projects
Home Farm
REPD record 4798. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 13 MW
- Status
- Abandoned
- Operator
- European Energy Photovoltaics
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Hartlepool
- Planning reference
- H/2014/0513
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-01-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-10-31: Planning Application Submitted
- 2015-04-21: Planning Permission Refused
- 2015-08-26: Appeal Lodged
- 2016-03-24: Appeal Granted
- 2016-03-24: Planning Permission Granted
- 2019-03-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4798. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.