Land at Havering Grove Farm
REPD record 4803. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Appeal Refused
- Operator
- Lightsource Renewable Energy
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Brentwood
- Planning reference
- 15/00161/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-02-16: Planning Application Submitted
- 2015-06-26: Planning Permission Refused
- 2015-10-28: Appeal Lodged
- 2016-05-23: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4803. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.