Hurst Hall
REPD record 4835. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 13.3 MW
- Status
- Appeal Refused
- Operator
- Green Switch Solutions
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire East
- Planning reference
- 14/4380N
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-03-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-22: Planning Application Submitted
- 2014-12-11: Planning Permission Refused
- 2015-06-04: Appeal Lodged
- 2016-02-12: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4835. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.