Lount solar farm
REPD record 4841. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 2.8 MW
- Status
- Operational
- Operator
- Hadstone Energy
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- North West Leicestershire
- Planning reference
- 14/00862/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-02-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-26: Planning Application Submitted
- 2014-12-17: Planning Permission Granted
- 2015-08-30: Under Construction
- 2015-11-30: Operational
- 2017-12-17: Planning Permission Expired
Open this area on the map