slava.energy: UK renewable energy projects
Tyddyn Cae (Nefyn)
REPD record 4862. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Operational
- Operator
- Lightsource Renewable Energy
- County
- Gwynedd
- Region
- Wales
- Country
- Wales
- Planning authority
- Gwynedd
- Planning reference
- C14/0885/33/LL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-12-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-09-08: Planning Application Submitted
- 2015-02-02: Planning Permission Granted
- 2015-07-27: Under Construction
- 2015-12-15: Operational
- 2020-02-02: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 4862. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.